Denis Ivanov Posted October 20, 2017 Report Posted October 20, 2017 Hi! Is it possible to mass change the tasks status? Like to select all tasks inside the shot and make them from "Not Started" to "In progress"? And also in any way to setup the default value for "Bid hours" and "Due date" ? Thanks in advance.
Alberto GZ Posted October 20, 2017 Report Posted October 20, 2017 7 minutes ago, Denis Ivanov said: Hi! Is it possible to mass change the tasks status? Like to select all tasks inside the shot and make them from "Not Started" to "In progress"? You can do multiple selection of desired tasks, then change its status, (by double-click in any of them pencil icon). If need, also you can set this from Tasks view in spreadsheet, and use filters to take your best selection.
Denis Ivanov Posted October 20, 2017 Author Report Posted October 20, 2017 Woo-hoo! All the secret is in the double-click. Many Thanks.