MyTask Pannel / statuses


jm Khayat

Recommended Posts

Hey all

When a task is created and assigned, it doesn't mean it can start right away. It's created but not available to start working on it.
So I've created a status to help people know when the task is ready to start - meaning the previous task of the shot has been completed.
The task is called "Ready 2 Start"

I've just realized my people don't see that task in MyTask even if they are assigned to the task, because the only status that allow them to see their assigned task is "Not started"

Is there a way to add more statuses allowed on myTask or is my current philosophy not aligned with Ftrack?

Thanks for any help

jm