Hi All,

Need some guidance setting up some projects templates for our PMs.

In a nutshell, I need to create predefined templates that will populate a projects with all the required tasks and milestones.

I've setup templates before, however i'm running into a few issues with this one in particular.

For reference, the structure of the project goes something like:

PROJECT X

1. Project Brief
  - Create Brief (TASK)
  - Review Brief (TASK)
  - Brief Agency (TASK)
  - Brief Internally (TASK)
  - Share Brief (TASK)

2. Create Concepts
  - Receive Concepts (TASK)
  - Review/Approve Concepts (VERSIONS/REVIEW/APPROVAL)
  - Share feedback with Agency (TASK)
  - Approve (REVIEW/APPROVAL)

3. Production Process
  - Review TV/Video Concepts (VERSIONS/REVIEW/APPROVAL)
  - Share with Management for Approval (REVIEW/APPROVAL)
  - Send RFP to (min) 3 Production Houses (TASK)
  - Receive Proposals (TASK)
  - Review Proposed Treatments (REVIEW/APPROVAL)
  - Review Quotations (TASK)
  - Select Production House (TASK)
  - Obtain management Approval (REVIEW/APPROVAL)
  - Raise PR/PO (TASK)
  - Proceed to Production

4. Production
  - Use existing template

5. Delivery
  - Approve Plan & PRF (REVIEW/APPROVAL)
  - Versions approval  (REVIEW/APPROVAL)
  - Adaptations (Social, Print etc)  (REVIEW/APPROVAL)
  - Final Approval  (REVIEW/APPROVAL)
  - Delivery

6. Reporting
  - Use existing template

 

OK, a bit convoluted I know - but that's our process. 

I realise a lot of these are not tasks, merely approvals, or could be Milestones, which is fine. The main issue I have is crafting a template that includes these Milestone - which I haven't figured out how to do.

When I add a list of task templates to a project, I can't manually insert Milestones - I can create them separately, but can't re-order the task list according to the hierarchy I want.

Also, generally, I'm not able to re-arrange tasks in the list - I try dragging tasks up and down but nothing happens.

 

Any help guys?

Thanks
Tony

Share this post


Link to post
Share on other sites

Hi Tony,

Unfortunately you cannot have Milestones in task templates. If you've a developer or have some python knowledge yourself you could do this as a Action instead, http://ftrack.rtd.ftrack.com/en/latest/using/actions.html , then you can make really custom things and tailor it to your liking

 

Share this post


Link to post
Share on other sites

OK, I'm trying to setup these projects, but Milestones are a bit of a pain. I've setup and Template and am manually adding Milestones, but can't drag/re-order the list. How comes?

Screenshot1.thumb.png.5e71af15e03fbe4151

Share this post


Link to post
Share on other sites

Also - can I have pre-defined Teams that I can select and assign, rather than adding them manually. Would be nice to have an option to set a Manager(s) for the project when creating new Projects too!

Share this post


Link to post
Share on other sites
On 4/18/2016 at 11:04 AM, Tony said:

Also - can I have pre-defined Teams that I can select and assign, rather than adding them manually. Would be nice to have an option to set a Manager(s) for the project when creating new Projects too!

It is not possible today but sounds like a good idea! I will make sure we have a feature request ticket for this

Share this post


Link to post
Share on other sites
2 hours ago, Tony said:

Thanks Matt - what about the re-ordering issue above?

Do you mean like sort it so that it appears under the Task, or as a child item to the task? Tasks cannot have any child items under them - not even milestones (they can be linked though) 

As for re-ordering you can enable it under the configuration wheel > Manual sort

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
2 2