Task dependency


Aleksander

Recommended Posts

Posted

20131022074032452.png

 

I was wondering something about task dependencies. 

 

Is it possible to link the "render" task to the "modeling" task so if I move the the time of the modeling task the render task automaticly follows. So if the end date is pushed of back one day, the start date for the render is also pushed back one day, without moving the end date of the shot?

 

Regards, 

Aleksander

Posted

Yes, in the gantt scheduler you can hold down cmd(on osx) or ctrl(on windows/linux) when moving a task to automatically adjust the dependencies.

 

This feature is however only available when drag and dropping in the gantt.

 

Cheers,

Carl