KateV@FatFree Posted July 17, 2018 Report Posted July 17, 2018 I am trying to move blocks of a project from one date to another, or from one user to another in the project Overview, using drag and drop, but even though visually the block moves to the new date / user it just 'pings' back to the original position. WHY? am I doing something wrong?
Mattias Lagergren Posted July 19, 2018 Report Posted July 19, 2018 Hi Kate, do you have the correct permission setup to change calendar events? There are two relevant permissions "Manage global events", "Manage project events". If that is not the issue, please open a support ticket and we will investigate this as a possible bug