Luigi Posted December 12, 2017 Report Share Posted December 12, 2017 When scheduling tasks and users in the task view it's really useful to see now the project plan and the resource timeline on the bottom of the gantt diagram. Unfortunately it's getting very confusing, since the 3 timelines could have different scales and positions in time. I have always to match the timelines to have a good overview and to see on the same date line if I can schedule a user and if it is still fitting to my plan If I'm not manually matching the 3 timelines I'm looking e.g. into my gantt schedule from January 29th till the 13th of February, the project plan is focusing between December 29th and January 19th and the resource timeline is showing dates between December 24th and January 13th. Even manually I'm not 100% able to have all dates in one line. Would it be better to scale and move all tree timelines at the same time, with the same (one) method? P.S.: I have still issues to upload screenshots "There was a problem processing the uploaded file. Please contact us for assistance. " Link to comment Share on other sites More sharing options...
Mattias Lagergren Posted December 13, 2017 Report Share Posted December 13, 2017 Hi Luigi, I completely agree and we are aware of this issue. This is technically challenging since we are mixing widgets from the old and new technology stack. But I will raise this again with the team and make sure they are aware of this. Link to comment Share on other sites More sharing options...
Luigi Posted December 13, 2017 Author Report Share Posted December 13, 2017 Thank you very much Link to comment Share on other sites More sharing options...
Recommended Posts
Archived
This topic is now archived and is closed to further replies.